How to Build a Commercial Renovation Budget (and How Much Contingency to Carry)

A renovation budget is more than a contractor's price. Here is what belongs in it, how much to hold back for the unknown, and how that number should shrink as the design firms up.

Key takeaways

  • Construction is only part of the cost. In Cushman & Wakefield's 2026 Toronto example, furniture, IT, A/V and soft costs add about 50% on top of the fit-out.
  • Canadian architects' guidance puts contingency as high as 25% early in design, falling to 2%–5% as uncertainty is reduced, and higher for renovations.
  • Keep design contingency, construction contingency and escalation as separate lines.
  • Base contingency on the real risks in your building, not a habit.

01 — Structure

What goes into a commercial renovation budget

A commercial renovation budget that only shows the construction price will run short. Cushman & Wakefield's 2026 Office Fit Out Cost Guide shows the full picture for a Toronto office: an average fit-out cost of $204.45 per sq ft, with other categories calculated as a percentage on top of it.

Example all-in budget structure for a Toronto office fit-out (Cushman & Wakefield, 2026)
Budget lineBasisPer sq ft
Fit-out constructionPhysical construction only$204.45
Soft costs10% of construction$20.45
IT4% of construction$8.18
A/V12% of construction$24.53
Furniture22% of construction$44.98
Miscellaneous2% of construction$4.09
All-in totalConstruction plus all categories above$306.68

A restaurant or retail renovation has different proportions, with more equipment and signage and often less furniture, but the logic is the same. Soft costs include design, engineering and permits. In Toronto, for example, the 2026 permit fee for interior alterations is $11.53 or $12.45 per square metre depending on the occupancy group. Cushman & Wakefield's construction breakdown also carries its own contingency line of $14.31 per sq ft, about 7% of the hard-cost total.

These are market figures from public 2026 sources, shown to help you plan. They are not XBuilt quotes. Every project is priced after a site visit and a review of your drawings.

02 — Contingency

How much contingency to carry on a renovation

Contingency is money set aside for risks you can name but cannot yet price. The Royal Architectural Institute of Canada's Canadian Handbook of Practice says contingencies may be as high as 25% at the early stages of a project and decrease to 2%–5% as the degree of uncertainty is reduced. It adds that construction contingencies for renovation work are higher than for new buildings.

The Handbook also says every estimate should identify two different contingencies, plus escalation. Alberta's 2026 Project Cost Framework makes the same split and requires contingencies to be risk-based, warning that blanket percentage allowances should not be used without clear justification.

Design contingency

Shrinks to zero
  • Covers scope not yet drawn or priced
  • Largest at concept and schematic design
  • Reduced as drawings develop
  • Should be nil once construction documents are complete

Construction contingency

Stays until closeout
  • Covers changes and unforeseen conditions after award
  • Also called post-contract or change order contingency
  • Higher on renovations of existing buildings
  • Tracked against cost-to-complete during the work
Do not spend contingency on upgrades. Contingency exists for risk. If you want better finishes, add them to the scope and the budget openly, so the reserve is still there when the ceiling comes down and something unexpected is behind it.

03 — Accuracy

How accurate is your estimate at each stage?

Contingency should match the accuracy of the estimate. Alberta's 2026 Project Cost Framework sets out typical accuracy ranges by design stage, using the common Class 5 to Class 1 scale:

Typical estimate accuracy by design stage (Government of Alberta, Project Cost Framework, 2026)
Design stageEstimate classTypical accuracy
Functional programClass 5−30% to +50%
Schematic designClass 4−20% to +30%
Design developmentClass 3−15% to +20%
Construction drawings, 50%–75%Class 2−10% to +15%
Pre-tender drawings, 95%–100%Class 1−5% to +10%

Estimate accuracy range by class

How far the final cost can typically fall below or above the estimate. Hover a bar for details.

Source: Government of Alberta, Project Cost Framework for Alberta Infrastructure Projects (May 2026). The axis runs from −50% to +50% around the estimate.

Notice that every range leans upward. Early estimates are far more likely to be low than high, which is exactly why early contingency needs to be generous.

04 — Escalation

Escalation is not contingency

Escalation is the expected change in prices between the date of the estimate and the date the work is bought. Altus Group's Canadian Cost Guide reminds users to account for construction cost escalation between the guide's date and the start of construction, and Alberta's 2026 framework requires escalation to be shown as a separate line item.

For 2026–2027 projects, two reference points help. Statistics Canada's Toronto non-residential construction price index rose 3.2% year over year in Q2 2026. Turner & Townsend's Q2 2026 forecast for Canada is 2.75% for 2026 and 4.0% for 2027. Our article on Toronto construction costs in 2026 explains what is behind those numbers.

05 — Existing buildings

Why renovation budgets need more room

In a new building, the designer controls almost everything. In a renovation, the building has a say. Common sources of surprises include:

  • Conditions hidden behind walls, ceilings and floors
  • Designated substances, such as asbestos. In Ontario, the owner must identify them and give the list to the constructor before signing the contract
  • Existing electrical, plumbing and HVAC that cannot support the new layout
  • Accessibility upgrades triggered by the scope of work
  • Phasing, after-hours work and access limits in occupied buildings

Alberta's framework asks that the scope narrative reflect the true condition of the facility and that renovation scope be priced separately from new work. Investigation before design, such as opening a few ceiling tiles or testing suspect materials, is usually the cheapest way to reduce the contingency you need. Our commercial renovations team walks the space with this in mind.

06 — Method

Five steps to a renovation budget you can defend

  1. Investigate the building

    Survey existing conditions and designated substances before the design is fixed.

  2. List every cost category

    Construction, design and permits, IT, A/V, furniture, equipment and moving.

  3. Set contingency by stage and risk

    Generous early, smaller as drawings develop, and higher for older buildings.

  4. Add escalation separately

    Use current forecasts and the expected date you will sign the construction contract.

  5. Track it monthly

    Compare contingency used against the work still to do, and release it only for real risks.

If you are planning a renovation in Toronto or the GTA, request a quote. XBuilt prices every project after a site visit, so the estimate reflects the building you actually have. See also our holdback guide on prompt payment in Ontario, which affects cash flow during the job.

07 — FAQ

Renovation budget FAQ

How much contingency should I carry on a commercial renovation?

It depends on how far the design has progressed and how much is unknown about the building. The Royal Architectural Institute of Canada's Handbook of Practice says contingencies may be as high as 25% at the early stages of a project and decrease to 2% to 5% as uncertainty is reduced, and that construction contingencies for renovation work are higher than for new construction.

What is the difference between design contingency and construction contingency?

Design contingency covers scope that is not yet drawn or priced, and it should shrink to zero once construction documents are complete. Construction contingency, sometimes called post-contract or change order contingency, covers changes and unforeseen conditions after the contract is signed. Alberta's 2026 Project Cost Framework requires the two to be shown as separate line items.

Should escalation be part of the contingency?

No. Escalation is the expected change in prices between the estimate and construction, so it should be its own line. Turner and Townsend's Q2 2026 forecast for Canada is 2.75% for 2026 and 4.0% for 2027.

Sources

  1. Cushman & Wakefield — Office Fit Out Cost Guide (2026)
  2. Royal Architectural Institute of Canada — Canadian Handbook of Practice, Chapter 4.2: Construction project cost planning and control
  3. Government of Alberta — Project Cost Framework for Alberta Infrastructure Projects (May 2026)
  4. Altus Group — Canadian Cost Guide
  5. Turner & Townsend — Canada Market Intelligence Q2 2026: Escalation forecast
  6. Statistics Canada — Building construction price indexes table, Q2 2026
  7. City of Toronto — Building permit fees (effective January 1, 2026)
  8. Government of Ontario — Guide to the Occupational Health and Safety Act, Part III

Budget your renovation

Start with
a number
you can trust.

Tell us about the space, the scope and your timeline. We reply to qualified requests the same business day.

+1 (647) 398-9960 info@xbuilt.ca
Your request goes directly to info@xbuilt.ca.