Key takeaways
- Statistics Canada's Toronto non-residential price index rose 3.2% year over year in Q2 2026, slower than the 4.2% recorded in Q3 2025.
- Altus Group says overall Toronto costs stabilized in 2025, with competitive mechanical and electrical pricing and flat labour costs.
- Metals tied to US tariffs and higher fuel prices are the main upward pressures.
- Turner & Townsend forecasts national escalation of 2.75% in 2026 and 4.0% in 2027.
01 — The data
Construction costs in Toronto in 2026: the official numbers
The most reliable public measure of construction costs in Toronto in 2026 is Statistics Canada's building construction price index. It tracks what contractors charge to build a set of model buildings, including an office building, a warehouse, a shopping centre and a factory. For Toronto's non-residential buildings, the index has kept rising, but at a slower pace than a year ago.
| Quarter | Toronto index | Change vs. previous quarter | Change vs. one year earlier |
|---|---|---|---|
| Q2 2025 | 108.1 | +1.3% | +3.9% |
| Q3 2025 | 108.9 | +0.6% | +4.2% |
| Q1 2026 | 109.8 | +0.2% | +2.9% |
| Q2 2026 | 111.7 | +1.3% | +3.2% |
Two things stand out. First, Toronto's non-residential increase of 3.2% in Q2 2026 was slightly below the 3.5% rise in Statistics Canada's 15-city composite. Second, the residential side moved the other way: Toronto's residential index fell 0.8% in the same quarter, the largest quarterly drop among the 15 cities, and was up only 0.1% over the year. A quieter housing market is part of the backdrop to the competitive trade pricing that Altus Group describes below.
Source: Statistics Canada, Building construction price indexes, tables for Q2 2025, Q3 2025, Q1 2026 and Q2 2026. Q2 2026 is the latest quarter published as of October 2026.
02 — Benchmarks
What does commercial construction cost per square foot in the GTA?
An index shows direction. To size a budget, you need dollar benchmarks. Altus Group's 2025 Canadian Cost Guide, an annual benchmark built on data from thousands of Canadian projects, gives these GTA hard-cost ranges:
| Building or scope | Market range per sq ft |
|---|---|
| Office interior fit-out, Class B | $110 – $150 |
| Office interior fit-out, Class A | $160 – $265 |
| Retail, strip plaza | $235 – $295 |
| Retail, big box store | $165 – $240 |
| Industrial, warehouse | $80 – $180 |
| Office building under 5 storeys, Class B | $260 – $355 |
GTA hard-cost ranges by building type
Canadian dollars per sq ft. Hover a bar for details.
For interiors, Cushman & Wakefield's 2026 Office Fit Out Cost Guide puts the average Toronto fit-out at $204.45 per sq ft, down from $210.09 in the previous edition. That drop matches what Altus describes: Toronto prices levelled off rather than continuing to climb. For more on interiors, see our office fit-out cost guide and our tenant improvements page.
These are market ranges compiled from public 2025–2026 sources for the Toronto area, shown to help you plan. They are not XBuilt quotes. Every project is priced after a site visit and a review of your drawings.
03 — Drivers
What is pushing Toronto construction prices up, or holding them down
Altus Group's 2026 commentary describes costs as shaped by structural factors, such as labour availability, regulatory complexity, trade policy and geopolitics, more than by ordinary inflation. These are the main forces for Toronto commercial work, ranked by their typical impact on a project budget:
Metals and tariffs
Altus names steel, aluminum and metal-bearing mechanical and electrical components as the dominant pressure. In Q2 2026, Statistics Canada recorded non-residential structural steel framing up 2.2% and metal fabrications up 2.0% in one quarter.
Fuel and transport
Statistics Canada cites higher oil and fuel prices raising machinery, equipment and delivery costs. Turner & Townsend reports diesel up 18.2% in Q1 2026.
Labour
In Toronto, Altus describes labour costs as largely flat and availability as plentiful. Nationally, construction job vacancies reached 3.2% in March 2026.
Trade competition
With residential construction slowing, Altus reports mechanical and electrical pricing in Toronto has flattened and become competitive.
Some materials easing
Turner & Townsend reports copper tube and pipe down 12.4% and ready-mixed concrete down 0.5% in Q1 2026. Altus says lumber has softened or stabilized.
04 — Outlook
Outlook: a cautious 2026 and a busier 2027
Altus Group's 2026 outlook is "cautious in 2026, optimistic for 2027". Its Toronto advisors go further, describing now as a good time to start new construction, with pricing near its most affordable in three to five years. The wildcard they name is a possible recession, which could push costs down further.
Turner & Townsend's Q2 2026 Canada Market Intelligence forecasts national bid price escalation of 2.75% in 2026, 4.0% in 2027 and 4.5% in 2028, with a range of plus or minus 2 percentage points. It expects tighter labour and supply chains in 2027 to increase competition for skilled workers. These are national figures, and the firm notes that escalation varies by province and project.
05 — Planning
What this means for your 2026 project budget
Price against current benchmarks
Use 2025–2026 data, not numbers from the peak years. Toronto fit-out averages have eased.
Watch metal-heavy scopes
Steel framing, storefronts, ductwork and electrical gear carry the most tariff risk. Order long-lead items early.
Carry escalation as its own line
If construction starts in 2027, plan for higher escalation than in 2026.
Size your contingency
Base it on the risk in your building and the stage of design. Our contingency guide explains how.
Get a site-based price
Benchmarks are a starting point. A walk-through turns them into a real number.
XBuilt prices commercial work across Toronto and the GTA, from commercial construction and renovations to restaurant and retail fit-outs. Request a quote and we will price your project line by line after a site visit.
06 — FAQ
Toronto construction costs FAQ
Are construction costs in Toronto going up in 2026?
Non-residential costs are still rising, but more slowly. Statistics Canada's building construction price index for Toronto non-residential buildings rose 1.3% in the second quarter of 2026 and 3.2% year over year. Toronto's residential index fell 0.8% in the same quarter.
What is driving construction prices in Toronto?
Altus Group's 2026 Cost Guide commentary points to metals such as steel and aluminum, tied to US tariffs and trade uncertainty, as the main material pressure, while Toronto labour costs are largely flat and mechanical and electrical pricing has become competitive. Statistics Canada also cites higher oil and fuel prices.
How much should I allow for cost escalation?
Turner and Townsend's Q2 2026 Canada Market Intelligence forecasts national bid price escalation of 2.75% for 2026, 4.0% for 2027 and 4.5% for 2028, with a range of plus or minus 2 percentage points. Projects starting later should carry an escalation allowance as its own budget line.
Sources
- Statistics Canada — Building construction price indexes, second quarter 2026
- Statistics Canada — Building construction price indexes table, Q2 2026
- Statistics Canada — Building construction price indexes table, Q1 2026
- Statistics Canada — Building construction price indexes table, Q3 2025
- Statistics Canada — Building construction price indexes table, Q2 2025
- Altus Group — Altus Group releases its 2026 Canadian Cost Guide (2026)
- Altus Group — Cautious in 2026, optimistic for 2027: Cost Guide insights (2026)
- Precedent Developments — 2025 Canadian Construction Costing Guide (GTA benchmarks from Altus Group's 2025 Canadian Cost Guide)
- Cushman & Wakefield — Office Fit Out Cost Guide (2026)
- Turner & Townsend — Canada Market Intelligence Q2 2026: Escalation forecast
- Turner & Townsend — Canada Market Intelligence Q2 2026: Construction input cost analysis
- Rider Levett Bucknall — North America Crane Index, Q1 2026