Key takeaways
- Cushman & Wakefield's 2026 guide puts the average Toronto office fit-out at $204.45 per sq ft for construction and $306.68 all-in.
- Turner & Townsend's 2025 Toronto ranges: $235–$395 per sq ft for medium-quality fit-out, $475–$865 for high quality (hard costs).
- Electrical is the largest construction trade; furniture is the largest cost on top of construction.
- Allowances of $50–$80 per sq ft (Class B and suburban GTA, 2026) usually cover only part of the build.
01 — The numbers
What does an office fit-out cost in Toronto in 2026?
Two established cost consultancies give a consistent picture of office fit-out cost in Toronto. Cushman & Wakefield's 2026 Office Fit-Out Cost Guide puts the average Toronto fit-out at $204.45 per square foot for physical construction, slightly down from $210.09 in the previous edition. With soft costs, IT, A/V, furniture and miscellaneous items added, the same guide reaches an all-in figure of $306.68 per square foot.
Turner & Townsend's Canadian cost data, published in January 2025, gives ranges by quality for Toronto: $235 to $395 per square foot for a medium-quality fit-out and $475 to $865 for high quality, in hard construction costs only.
Toronto office fit-out, cost per square foot
Canadian dollars per sq ft. Hover a bar for details.
For context, JLL's 2026 guide for the U.S. and Canada combined puts a medium-quality corporate fit-out at about US$295 per square foot, with a typical range of US$230 to US$375. It notes that Canadian markets sit at a distinct cost level but does not publish a Toronto-only number.
These are market ranges compiled from public 2025–2026 sources for the Toronto area, shown to help you plan. They are not XBuilt quotes. Every project is priced after a site visit and a review of your drawings.
02 — Breakdown
Where the money goes, trade by trade
Cushman & Wakefield breaks its Toronto figure into trades. Electrical is the largest single line, followed by general requirements and fee, and drywall, acoustic and carpentry.
| Component | What it covers | Per sq ft |
|---|---|---|
| Electrical | Power, lighting, panels and devices | $42.93 |
| General requirements, conditions and fee | Site management, general conditions and the contractor's fee | $36.80 |
| Drywall, acoustic, carpentry | Partitions, bulkheads, ceilings | $32.71 |
| Mechanical, plumbing, fire protection | HVAC distribution, plumbing, sprinkler work | $24.53 |
| Doors, frames, hardware | Suite entry, offices, meeting rooms | $22.49 |
| Contingency | Allowance for unknowns | $14.31 |
| General finishes | Flooring, paint, wall finishes | $12.27 |
| Architectural millwork | Reception, kitchenettes, built-ins | $8.18 |
| Miscellaneous architectural trades | Specialties and other architectural items | $8.18 |
The guide lists a total of $202.40 for these components, against a headline of $204.45; use the breakdown as proportions rather than an exact sum.
Costs on top of construction
Construction is only part of the project. Cushman & Wakefield adds these items as percentages of hard costs for Toronto:
| Item | Share of hard costs | Per sq ft |
|---|---|---|
| Furniture | 22% | $44.98 |
| Audio-visual | 12% | $24.53 |
| Soft costs (design, fees) | 10% | $20.45 |
| IT cabling | 4% | $8.18 |
| Miscellaneous | 2% | $4.09 |
03 — Budget
What drives the cost of an office fit-out
Two offices of the same size can land far apart. These factors usually move the budget most, ranked by typical impact:
Finish level and density
High-quality fit-outs run roughly double medium quality in Turner & Townsend's ranges. Private offices and meeting rooms add walls, doors and ductwork.
Electrical and lighting
The largest single trade in the Toronto breakdown at $42.93 per sq ft.
Condition of the space
Reusing a second-generation layout versus demolishing it or starting from a bare shell.
Mechanical and sprinklers
New ductwork, supplementary cooling for server or meeting rooms, sprinkler relocation.
Technology and A/V
Meeting-room A/V alone adds 12% of hard costs in the 2026 Toronto guide.
Schedule and building rules
After-hours work for noisy trades, elevator bookings and landlord review periods.
Where prices are heading
Statistics Canada reported that non-residential building construction prices rose 1.4% in the second quarter of 2026, and 3.5% year over year across its composite of 15 metropolitan areas, citing fuel prices, tariffs and a constrained skilled-trades workforce. Cushman & Wakefield also reports that contractors expect labour and material prices to keep rising. Lock in pricing as close to your lease decision as you can.
04 — Who pays
How much will the landlord cover?
A tenant improvement allowance rarely covers the whole build. ENCOR Advisors reported in 2026 that TI packages of $50 to $80 per square foot are achievable in Class B and suburban GTA buildings. Against an average construction cost of about $204 per square foot, most tenants fund the difference themselves. Our guide to tenant improvement allowances in Ontario covers how allowances are paid and what to negotiate, and base building vs. fit-out explains what the landlord should already be providing. Have a lawyer review the lease terms before you sign.
05 — Schedule
Permits and timing for a Toronto office fit-out
An office interior alteration in Toronto needs a building permit. Office suites up to 600 m² with no change of use may qualify for the City's Express Service, which targets a review within 3 business days. Larger projects go through the Small Building (15 business days) or Large/Complex (20 or 30 business days) streams, counted from a complete application that includes a Zoning Applicable Law Certificate.
XBuilt builds office tenant improvements, commercial renovations and offices inside warehouses across Toronto and the GTA, with site work scheduled outside regular hours when the building requires it. Request a quote to get your space priced after a site visit.
FAQ
Office fit-out cost FAQ
How much does an office fit-out cost per square foot in Toronto?
Cushman & Wakefield's 2026 guide puts the average Toronto office fit-out at $204.45 per square foot for construction and $306.68 all-in with soft costs, IT, A/V, furniture and miscellaneous items. Turner & Townsend's 2025 data shows $235 to $395 per square foot for a medium-quality fit-out and $475 to $865 for high quality, in hard costs only.
What is the biggest cost in an office fit-out?
In Cushman & Wakefield's 2026 Toronto breakdown, electrical is the largest construction trade at $42.93 per square foot. Outside construction, furniture is the largest added cost at 22% of hard costs.
Does the landlord pay for an office fit-out?
Often partly. Landlords may offer a tenant improvement allowance; a Toronto brokerage reported in 2026 that $50 to $80 per square foot is achievable in Class B and suburban GTA buildings. That usually covers only part of the build, so tenants should price the fit-out before signing and have a lawyer review the lease.
Sources
- Cushman & Wakefield — Office Fit-Out Cost Guide 2026, Canada
- Turner & Townsend — Canada market intelligence Q4 2024–2025, annual cost guide (January 2025)
- Turner & Townsend — Canada cost data table 2025 (PDF)
- JLL — U.S. and Canada Office Fit-Out Costs Guide 2026
- Statistics Canada — Building construction price indexes, second quarter 2026
- ENCOR Advisors — Office lease renewal in Toronto (April 2026)
- City of Toronto — Building permit review streams
- City of Toronto — Interior alterations (non-residential) permit guide