Restaurant service counter with display case and tile wall during construction

Construction holdback and prompt payment in Ontario

Ontario's Construction Act decides how much you hold back, how fast you pay and what happens when an invoice is disputed. Several rules changed on January 1, 2026. Here is what owners and tenants need to know.

Key takeaways

  • The construction holdback in Ontario is 10% of the value of work and materials supplied, retained by the owner to protect lien claimants down the chain.
  • Owners must pay a proper invoice within 28 days; contractors pay their subcontractors within 7 days after being paid.
  • Since January 1, 2026, invoices are deemed proper unless the owner objects within 7 days, and holdback must be released every year on the contract anniversary.
  • Payment disputes can go to adjudication, and amounts ordered by an adjudicator are now due within 15 days.

This article is general information about Ontario's Construction Act for business owners. It is not legal advice. Contracts, dates and exceptions matter, so speak to a construction lawyer about your project.

01 — The basics

How the construction holdback works in Ontario

The construction holdback is money the owner keeps back from every payment on a construction contract in Ontario. The basic holdback is 10% of the value of the services and materials supplied. It exists because subcontractors and suppliers further down the chain have lien rights against the property; the holdback is the fund that protects them, and it protects the owner too, because an owner who holds back properly limits its exposure to those liens. An owner that fails to retain it can be personally liable.

A simple example: on a $400,000 fit-out paid in monthly progress draws, an invoice for $100,000 of completed work is paid at $90,000, and $10,000 is retained. By the end of the job the holdback fund is $40,000.

Liens and their deadlines

A contractor or supplier who is not paid can register a lien against the property. The deadlines did not change in 2026: a lien must be preserved within 60 days of the earlier of published substantial performance, or completion, abandonment or termination of the contract, and then perfected within a further 90 days, for a total of up to 150 days.

02 — 2026 amendments

What changed on January 1, 2026

Two bills, Bill 216 (2024) and Bill 60 (2025), amended the Act with effect from January 1, 2026. The biggest change is that holdback no longer sits untouched until the end of a long project.

Key Construction Act rules before and after the January 1, 2026 amendments (Robins Appleby LLP, 2026; Miller Thomson, 2019)
RuleBefore 2026From January 1, 2026
Holdback releaseGenerally after lien rights expired at the end of the job. Phased or annual release only where the contract price exceeded $10M and the contract provided for it.Mandatory annual release on each contract anniversary. Notice within 14 days after the anniversary, payment within 74 days.
Holdback to subcontractorsPaid down the chain after release.Contractor pays subcontractors within 14 days of receiving it.
DeficienciesOwners often relied on holdback as security.Holdback cannot be withheld for deficiencies or corrective work, and parties cannot contract out of this.
Proper invoiceOwner could reject a non-compliant invoice.Deemed proper unless the owner objects in writing within 7 days, naming the deficiency.
Adjudication paymentWithin 10 days of the determination.Within 15 days of the determination.

Annual release applies immediately to contracts entered into on or after January 1, 2026. For earlier contracts, the first annual release is pushed to the second anniversary after that date: a contract signed on January 15, 2023, for example, has its first release on January 15, 2027. Release is delayed while a preserved or perfected lien remains unresolved.

03 — Timelines

Prompt payment timelines on a commercial project

Prompt payment has applied in Ontario since 2019. The clock starts when the owner receives a proper invoice: an invoice with the information the Act requires, which can now include details the owner reasonably needs for its accounts payable system. If the contract does not say otherwise, invoices are issued monthly.

DAY 0Invoice receivedThe owner receives the contractor's invoice.
DAY 7Objection deadlineObject in writing or the invoice is deemed proper.
DAY 14Notice of non-paymentThe owner's last day to dispute all or part of the amount.
DAY 28Owner paysUndisputed amounts, less the 10% holdback.
+7 DAYSSubcontractors paidThe contractor pays its trades within 7 days of being paid.
ANNUALLYHoldback releasedOn the contract anniversary for contracts from 2026.

The same 28-7-7 pattern runs down each tier, and the parties cannot contract out of it. A contractor that was paid in full but disputes a subcontractor's claim must give its own notice of non-payment, within 35 days after it delivered the proper invoice to the owner.

04 — Disputes

Adjudication: quick decisions on payment disputes

Adjudication is a fast, interim process for construction disputes, run through the Ontario Dispute Adjudication for Construction Contracts (ODACC). An adjudicator decides on the documents within a short timeline, and the decision is binding until a court or arbitrator says otherwise. When adjudication launched, the rules gave the adjudicator 30 days from receiving the referring party's documents to make a determination, unless the parties agreed otherwise.

The 2026 amendments widened what can be adjudicated and changed a few deadlines:

  • Payment disputes, holdback payment, scope of work, change-order pricing and extension-of-time requests can all be referred.
  • A referral must generally be made within 90 days of completion, abandonment or termination, unless the parties agree otherwise.
  • Parties can agree on a private adjudicator qualified under ODACC whose fees total at least $1,000.
  • Amounts ordered by an adjudicator are due within 15 days, up from 10.

05 — In practice

What owners and tenants should do now

Most of the new rules reward owners who are organized. A few habits make them easy to live with:

  1. Review invoices within the week

    The 7-day objection window is short. Make sure invoices reach the right person on day one and are checked against the schedule of values.

  2. Diarize the contract anniversary

    Put the anniversary, the 14-day notice and the 74-day payment deadline in your calendar, and plan the cash for each release.

  3. Secure deficiencies another way

    Holdback can no longer cover deficiencies, so agree in the contract how incomplete or corrective work will be handled.

  4. Use a current contract form

    Standard forms such as CCDC 2 are updated for prompt payment; older custom contracts may not reflect the 2026 rules.

  5. Budget for timing, not just cost

    Earlier holdback releases change cash flow. Our guide to budgeting a commercial renovation explains how to plan contingency.

At XBuilt we invoice on a clear schedule of values and walk owners through the payment steps before construction starts, whether the project is a tenant improvement or a full commercial build-out. If you are comparing contractors, read how to choose a commercial general contractor in Toronto, or request a quote for your project.

06 — FAQ

Holdback and prompt payment FAQ

What is the holdback percentage in Ontario construction?

The basic holdback under Ontario's Construction Act is 10% of the value of the services and materials supplied under the contract. The owner retains it from each payment to protect subcontractors and suppliers who have lien rights.

How long does an owner have to pay a contractor in Ontario?

An owner must pay a proper invoice within 28 days of receiving it, or deliver a notice of non-payment within 14 days explaining what is disputed. Since January 1, 2026, an invoice is deemed proper unless the owner objects in writing within 7 days. The contractor then pays its subcontractors within 7 days of being paid.

When is holdback released under the 2026 rules?

For contracts entered into on or after January 1, 2026, accrued holdback must be released each year on the contract anniversary. The owner publishes a notice within 14 days after the anniversary and pays within 74 days, and the contractor pays its subcontractors within 14 days of receiving the money. Earlier contracts start annual release on the second anniversary after January 1, 2026.

Sources

  1. Robins Appleby LLP via Mondaq — Two key changes to Ontario's Construction Act, Bill 216 and Bill 60 (January 2026)
  2. Robins Appleby LLP via Mondaq — Key changes to Ontario's Construction Act, adjudication (July 2026)
  3. Nihang Law — Ontario's Construction Act changes in 2026 (liens, invoices, holdback)
  4. McCarthy Tétrault — Mandatory annual holdback release (2024)
  5. McCarthy Tétrault — A primer on the amendments to Ontario's Construction Act (prompt payment and adjudication, 2019)
  6. Miller Thomson — Holdback: what you need to know (2019)

Start your project

Clear terms.
Clean
build.

Tell us about the space, the scope and your timeline. We reply to qualified requests the same business day.

+1 (647) 398-9960 info@xbuilt.ca
Your request goes directly to info@xbuilt.ca.