Key takeaways
- The City of Toronto states that a change of use requires a building permit even if no construction is proposed.
- There are two separate questions: is the new use allowed by zoning, and is the building safe for it under the Building Code?
- A change of use rules a project out of Toronto's 3-day Express Service and can trigger upgrades to fire separations, exits, washrooms and ventilation.
- Check both before you sign the lease. A $214.79 Zoning Use Review is the cheapest first step.
01 — The basics
What counts as a change of use in Toronto?
A change of use in Toronto means using a building, or part of one, for a different purpose than the one it was approved and built for. The City's own example is converting residential space to office. In commercial leasing it often looks like an office becoming a clinic, a retail unit becoming a restaurant, or warehouse space becoming a gym or event venue.
The City is direct about the permit: even if no construction is proposed, if a change of use is proposed a building permit is required. Ontario's guide to building permits says the same thing in provincial terms: if you want to change the way you use all or part of a building, you may need a change of use permit, even if you are not planning any construction, and a building evaluation may be required to confirm the building can safely handle the new use.
The underlying rule sits in the Building Code Act, 1992. Section 10(1), as quoted in Ontario municipal guidance, says no person shall change the use of a building or part of a building if the change would result in an increase in hazard, unless a permit has been issued by the chief building official.
Same use, new tenant
Permit for the work- Retail to retail, office to office
- A permit is still needed for most alterations
- Small interior jobs may qualify for Express Service
- Existing exits and washrooms are a starting point
New use in the space
Permit even with no work- Zoning must permit the new use
- The building is evaluated for the new use
- Not eligible for Express Service
- Upgrades may be required to offset added hazard
02 — Zoning
Step one: confirm zoning allows the new use
Zoning answers whether a use is allowed at that address at all. If it is not, the provincial guide notes that a permit will not be issued until the zoning change or minor variance has been obtained. That can add months, so it belongs before the lease, not after.
Toronto offers several zoning tools. Picking the right one saves money and time:
| Step | What it answers | 2026 City fee |
|---|---|---|
| Zoning Use Review | Is the use permitted at this property? Covers uses such as commercial, restaurant, office, personal services, medical and manufacturing. No plans required. | $214.79 |
| Zoning Applicable Law Certificate (ZAP) | Full zoning and applicable law review of plans. Needed for drive-throughs, patios and uses not on the Use Review form, and before a building permit. | $888.14 (≤300 m²) · $1,863.82 (>300 m²) |
| Change of use permit | Building Code review of the new use when no construction permit is involved | Min. $297.41 + $92.79 per additional hour |
| Building permit with construction | Alterations plus the new use, reviewed together | Service Index × area (e.g. $11.53–$12.45/m²) |
Fees from City of Toronto Zoning Use Review, ZAP and building permit fee pages (2026). City fees only, not XBuilt quotes; design and construction are priced separately after a site visit. Rules and fees change, so confirm with Toronto Building.
Business licences depend on zoning too
Many commercial uses also need a business licence, and the licence follows zoning. For an eating or drinking establishment, for example, Toronto requires an approved Zoning Review for Business Licence before you apply. The exception is taking over an existing business with a valid licence, or one that expired less than three years ago, in the same licence category. The application and licence fees total $536.64.
03 — Building Code
Step two: the Building Code view of a change of use
Zoning asks "is this use allowed here?" The Building Code asks "is this building safe for this use?" Those are different questions, and a space can pass one and fail the other.
The Code groups uses into major occupancies. Toronto's review stream rules, for instance, refer to assembly and industrial uses (Groups A and F) and to business, office, retail and restaurant uses (Groups D and E). Moving between groups, or adding many more occupants, can change what the building needs: more exit capacity, better fire separations, more washroom fixtures.
For an existing building, the hazard level is measured under Part 10 of Division B of the Ontario Building Code. If the new use increases the hazard, upgrades may be needed to compensate. Ontario municipal guidance lists examples where a permit is required even with no construction, such as changing the major occupancy of all or part of a building in specified cases, or changing a use where the previous major occupancy cannot be determined.
Change of use and Express Service
Toronto's Express Service, with a 3-business-day review target, is limited to small commercial interior alterations with no change in use and no change in patron area. A change of use moves your project into the regular streams: 15 business days for Part 9 buildings, and 20 or 30 business days for large and complex Part 3 buildings, once the application is complete. Our step-by-step guide to commercial permits walks through those streams.
04 — Upgrades
What upgrades can a change of use trigger?
Not every change of use leads to construction, but when the hazard goes up, Ontario municipal guidance lists the areas where upgrades may be required:
Structural systems
Heavier floor loads or new equipment can require engineering review and reinforcement.
Demising walls and fire separations
New ratings between your unit and neighbours or corridors.
Exits and door hardware
More occupants can mean more or wider exits and different hardware.
Washrooms and plumbing fixtures
Fixture counts follow occupant load, and new washrooms bring barrier-free rules.
HVAC and ventilation
Fresh air and exhaust sized for the new use.
Life safety systems
Exit signs, emergency lighting and a fire alarm system if required.
Impact levels are typical and depend on the building. Washrooms are often the surprise item: see barrier-free washroom requirements in Ontario and our accessibility and washroom services.
05 — Planning
How to plan a change of use without losing months
Run the zoning check before you sign
A Zoning Use Review costs $214.79 and needs no plans. Make the lease conditional on the result where you can.
Ask for the permit history
Prior permits show the approved use and what was built. Gaps here create risk later.
Walk the space with your designer and contractor
Look at exits, demising walls, washrooms and mechanical capacity against the new use.
Price the upgrades into the deal
Who pays for code upgrades is a lease question. Our landlord's work vs. tenant's work guide covers how to split them.
Apply once, completely
Combine the new use and the alterations in one complete application with an issued ZAP.
XBuilt handles permit and inspection coordination on tenant improvement projects across Toronto and the GTA, working with design partners to get drawings right the first time. If you are considering a space for a new use, request a quote and we can walk it with you.
FAQ
Change of use FAQ
Do I need a permit if I change the use of a commercial unit but don't renovate?
Often, yes. The City of Toronto states that even if no construction is proposed, a change of use requires a building permit. Under the Building Code Act, a permit is required where the change would increase the hazard, and the City reviews whether the building can safely support the new use.
How do I check if a use is allowed at a Toronto address?
The City's Zoning Use Review confirms whether a proposed use complies with the zoning by-law at a specific property. It costs $214.79 in 2026 and needs no plans. Drive-throughs, patios and unlisted uses need a Zoning Applicable Law Certificate instead.
Can a change of use go through Toronto's Express Service?
No. Express Service for small commercial projects requires no change in use and no change in patron area. A change of use goes through the regular review streams, with target review times of 15 to 30 business days once the application is complete.
Sources
- City of Toronto — When do I need a building permit
- Government of Ontario — Citizens' guide to land use planning: building permits
- Brockville — Change of use building permits (quotes Building Code Act s. 10(1) and Part 10 upgrades, 2023)
- Township of Norwich — Change of use permits
- City of Toronto — Zoning Use Review (2026 fee)
- City of Toronto — Zoning Applicable Law Certificate (2026 fees)
- City of Toronto — Building permit fees (2026)
- City of Toronto — Building permit review streams
- City of Toronto — Eating or drinking establishment licence
