Key takeaways
- Toronto industry data puts lease signing to opening at 10 to 14 weeks for a quick-service refresh, 14 to 18 weeks for full-service, and 18 to 24 weeks for bare-shell or heavy-ventilation builds (2026).
- Toronto Building's review targets range from 3 business days (Express Service) to 30 business days for complex buildings, for complete applications only.
- A liquor licence typically takes four to six months, so it must start long before construction ends.
- Each permit resubmission can add two to three weeks. Complete drawings save more time than any crew on site.
01 — Overview
The restaurant build out timeline at a glance
A restaurant build out timeline in Toronto depends mostly on what the space was before you. A unit that was already a restaurant needs less work and simpler permits than a bare shell. The ranges below come from 2026 Toronto industry data and cover the whole journey, from lease signing to opening day.
| Project type | Lease to opening | Construction only |
|---|---|---|
| Quick-service refresh in an existing food space | 10 – 14 weeks | 6 – 8 weeks |
| Full-service restaurant | 14 – 18 weeks | 8 – 12 weeks |
| Bare-shell or heavy-ventilation build | 18 – 24 weeks | 10 – 14 weeks |
Weeks from lease signing to opening
Toronto market range. Hover a bar for details.
02 — Before you sign
Lease signing and due diligence
The clock starts at lease signing, so the most valuable work happens before it. Three items decide how long everything else takes:
- What the space was. A former restaurant may keep its hood, grease interceptor and electrical service. Our guide to second-generation restaurant space explains what to inspect.
- Zoning. Toronto requires an approved Zoning Review for Business Licence before you apply for an eating or drinking establishment licence, unless you take over a business with a valid licence, or one that expired less than three years ago in the same category.
- Asbestos. Under Ontario Regulation 278/05, the owner must have a report on materials likely to be disturbed before requesting tenders or arranging an alteration. Ask your landlord for it early.
Negotiate the fixturing period with the schedule in hand. One 2025 Canadian cost guide notes that landlords in soft markets may offer 4 to 12 weeks of rent-free occupancy during renovation, and recommends a 30 to 60 day buffer in the opening timeline.
03 — Approvals
Design and permits: where schedules are won or lost
Restaurants need coordinated architectural, mechanical, plumbing and kitchen drawings. Toronto Building only starts the clock on a complete application, which includes plans, an issued Zoning Applicable Law Certificate and paid fees. The City states plainly that there is no time frame for review of incomplete applications.
| Review stream | Applies to | Target review time |
|---|---|---|
| Express Service | Interior alterations to restaurants under 30 seats, up to 600 m², no change in use or patron area | 3 business days (goal) |
| Small Building | Buildings within Part 9 of the Building Code | 15 business days |
| Large Building | Buildings within Part 3 of the Building Code | 20 business days |
| Complex Building | Complex Part 3 buildings | 30 business days |
Targets from the City of Toronto. In practice, Toronto industry data puts typical restaurant tenant-improvement permits at 4 to 7 weeks to issuance, and each resubmission adds 2 to 3 weeks (CHI Real Estate, 2026).
Two parallel tasks belong in this phase. First, submit your plans to Toronto Public Health before construction; the City asks operators to contact Public Health before construction or renovation begins. Second, order long-lead items such as the hood, rooftop equipment and millwork so they arrive when the site is ready, not weeks later. If your concept needs a new hood, read our guide to kitchen exhaust hoods in Ontario before the drawings are finalized.
04 — On site
Construction and inspections
Construction for a quick-service refresh typically runs 6 to 8 weeks in Toronto, a full-service casual restaurant 8 to 12 weeks, and heavy-ventilation concepts 10 to 14 weeks (CHI Real Estate, 2026). Inside that window, inspections act as gates: work cannot be covered until it passes.
| Inspection | When to call |
|---|---|
| Plumbing rough-in | Water supply, drains, waste and vents complete and ready for testing |
| Rough-in kitchen exhaust | At completion of rough-in, before concealment |
| Fire separations | After framing and fire stopping, before finishes or lay-in ceiling tiles |
| Life safety systems | At rough-in, with referral to Toronto Fire Prevention |
| Final interior, plumbing and HVAC | At completion of construction and installation of fixtures and systems |
Toronto lets you request an inspection date from the next business day up to four weeks ahead, and for large buildings the City says inspections take place within two business days of the request. A contractor who books inspections ahead, in the right order, keeps trades from standing around. XBuilt's management team handles that sequencing on every restaurant construction project.
05 — Final stretch
Licences, health inspection and opening day
Toronto industry data allows 1 to 3 weeks after construction for final inspections and a soft opening. Three approvals have to land in that window or before it:
- Toronto Public Health inspection. After construction is finished, a public health inspector inspects the premises before opening and arranges the date with you.
- Business licence. An eating or drinking establishment licence costs $536.64 in application and licence fees combined, according to the City's licence page.
- Liquor licence. AGCO approval typically takes four to six months from application, and the premises must be ready for inspection within 30 days of submitting the application (CHI Real Estate, 2026). Plan the application date backwards from opening.
06 — Risks
What usually delays a restaurant opening
- Incomplete permit applications, which have no review time frame in Toronto.
- Permit resubmissions, each adding 2 to 3 weeks.
- Adding seats or patron area, which removes Express Service eligibility.
- A hood or grease interceptor that must be replaced after the lease is signed.
- Late liquor licence applications.
- Ceilings closed before the exhaust or fire separation inspection.
Industry guidance recommends a 15 to 20 percent budget contingency for unexpected conditions, especially in older buildings (CHI Real Estate, 2026). Building a schedule backwards from your opening date, with a contractor involved before you sign, is the most reliable way to hit it. Request a quote and we will map the phases against your lease. Multi-unit operators can see how we run several sites at once on our multi-location rollouts page.
FAQ
Restaurant build-out timeline FAQ
How long does it take to build out a restaurant in Toronto?
Toronto industry data for 2026 puts lease signing to opening at 10 to 14 weeks for a quick-service refresh in an existing food space, 14 to 18 weeks for a full-service restaurant, and 18 to 24 weeks for a bare-shell or heavy-ventilation build.
How long does a restaurant building permit take in Toronto?
Toronto Building's targets for complete applications range from 3 business days for eligible Express Service projects to 15, 20 or 30 business days depending on the building. Industry data puts typical restaurant tenant-improvement permits at 4 to 7 weeks, and each resubmission can add 2 to 3 weeks.
When should I apply for a liquor licence?
Early. AGCO approval typically takes four to six months, and the premises must be ready for inspection within 30 days of submitting the application, so plan the submission date backwards from your opening and construction schedule.
Sources
- CHI Real Estate — Toronto restaurant permits guide (2026)
- CHI Real Estate — Startup costs for opening a restaurant in Toronto (2026)
- Kim Ecopak — Restaurant startup costs in Canada (2025)
- City of Toronto — Building permit review streams
- City of Toronto — When to call for inspection of large buildings
- City of Toronto — About building inspections
- City of Toronto — Submitting plans to Toronto Public Health
- City of Toronto — Eating or drinking establishment licence
- IHSA — Asbestos: owner's duties under O. Reg. 278/05