Retail fit-out checklist: what to settle before construction starts

The decisions that protect a store opening date are made before anyone picks up a tool. Here is what to settle first, and in what order.

Key takeaways

  • Settle landlord's work vs. tenant's work, the deposit and designated contractors before you sign or hire designers.
  • Landlord design review comes first: published Toronto criteria allow 10 business days for each of two submissions.
  • Toronto's Express Service targets 3 business days for retail interior alterations up to 600 m² with no change in use.
  • Long-lead items and landlord site rules decide how fast the build actually moves.

01 — Lease

Start the retail fit-out checklist with the lease

Most retail fit-outs that open late were already late before the first stud went up. This retail fit-out checklist covers the decisions to settle before construction starts, in the order they usually come up for a store in Toronto or elsewhere in Ontario.

The lease decides who pays for what and which rules apply. Before you sign, or at the latest before you hire designers, confirm:

  • The split between landlord's work and tenant's work, in writing
  • The landlord's design criteria and construction manual, and which version applies
  • The construction deposit: one published Toronto manual asks for 3% of construction value, with a $1,000 minimum and a $10,000 cap
  • Which work must go to the landlord's designated contractors, such as sprinklers, fire alarm and base-building changes
  • Insurance limits for your contractor and consultants
  • Your fixturing period and opening date, and what happens if you miss it

If you are still negotiating, our construction checklist for commercial leases goes deeper on what to ask.

02 — Design

Lock the design against the landlord's criteria

In a mall or retail concourse, the landlord approves your design before the City sees it. Published criteria for one downtown Toronto property (2021, updated 2024) show the kind of limits to design around:

  • Store openings no wider than 40% of the storefront
  • Primary signage no longer than 40% of the storefront length
  • A landlord control zone covering the first 5'-0" behind the lease line, finished in hard surfaces such as natural wood, stone or porcelain
  • No vinyl or sheet flooring in sales areas, and no acoustical tile ceilings
  • Sprinkler heads concealed with cover plates

The same criteria set a two-step review. The preliminary package needs complete drawings and two sample boards; the final package needs five architectural sets plus four mechanical and four electrical. The landlord takes 10 business days for each step. Incomplete packages are not reviewed, so a missing sheet costs you a full cycle.

03 — Permits

Know which permit stream your store is in

Most interior alterations need a building permit, and signs need their own. Toronto Building sorts applications into review streams with different target times:

Toronto building permit review streams and targets for complete applications (City of Toronto, 2026)
StreamWhat it coversTarget review
Express Service, small commercialInterior alterations to retail, office and business uses (and restaurants under 30 seats) up to 600 m², no change in use, no active shell permit3 business days
Express Service, signsFirst-party and third-party sign permits, up to three signs3 business days
Small BuildingPart 9 buildings under the Building Code, excluding houses15 business days
Large BuildingPart 3 buildings20 business days
Complex BuildingComplex Part 3 buildings30 business days

An application only counts as complete once it includes an issued Zoning Applicable Law Certificate, among other items, and the City sets no time frame for incomplete applications. Always confirm current requirements with the City of Toronto before you apply.

A change of use, such as turning an office unit into a store, takes the project out of Express Service; see change of use in Toronto. For the full process, read our guide to commercial building permits in Toronto. One more filing: when labour and materials are expected to exceed $50,000, the constructor must file a Notice of Project with Ontario's Ministry of Labour before work begins.

04 — Building services

Confirm power, HVAC, sprinklers and data

Retail looks light on services compared with a restaurant, but lighting, signage, HVAC and security still have to tie into the building. Settle these before the drawings are final:

  • Capacity. If you need more electrical or HVAC capacity than the landlord provides, one published manual makes the tenant pay the landlord's costs, including incremental capital costs.
  • Base-building work. Changes to base-building systems, fire detection and structure go to landlord-designated contractors at the tenant's expense.
  • Sprinkler layout. Moving heads for new ceilings or bulkheads needs the landlord's approval and usually the base-building sprinkler contractor.
  • Coring and cutting. One 2025 manual requires x-rays before any coring, at the tenant's expense, with coring above occupied floors only after 10:00 p.m.
  • Data and security. Plan cabling for point-of-sale and cameras early. In one manual, security systems installed without approval are removed at the tenant's expense.

05 — Schedule and site rules

Order long-lead items and agree on site rules

Millwork, fixtures, signage and lighting are usually built to order, so they need approved drawings before they can be released. Then the site rules decide how fast the crew can work. One Toronto manual (2025) keeps tenant work outside normal business hours (7:30 a.m. to 6:30 p.m. weekdays, 9:00 a.m. to 5:00 p.m. Saturday) unless the landlord approves otherwise, routes all deliveries through the loading dock and refuses unscheduled ones, and allows only low-odour, low-VOC paints and sealers.

PHASE 01Lease and criteriaWork split, deposit, designated contractors, opening date.
PHASE 02Landlord reviewPreliminary and final packages, 10 business days each.
PHASE 03PermitsFrom 3 business days for Express Service retail alterations.
PHASE 04OrdersMillwork, fixtures, signage and lighting released.
PHASE 05ConstructionBuilt to the landlord's hours, delivery and hoarding rules.
PHASE 06CloseoutInspections, deficiencies and landlord documents.

06 — On one page

The retail fit-out checklist at a glance

What to settle, and by when (based on City of Toronto 2026 permit streams and published Toronto landlord criteria, 2021–2025)
ItemSettle beforeWhy it matters
Landlord's work vs. tenant's workLease signingDefines what your budget covers
Criteria package and construction manualLease signingSets materials, contractors and working hours
Deposit, fees and insurance limitsLease signingNeeded in hand before work can start
Storefront and signage designPreliminary submissionThe landlord approves it first
Full architectural, mechanical and electrical drawingsFinal submissionIncomplete packages are not reviewed
Building and sign permitsMobilizationExpress Service from 3 business days if eligible
Notice of ProjectMobilizationRequired above $50,000 in labour and materials
Long-lead ordersFinal approvalProtects the opening date
Closeout documentsOpening, plus 60 daysSome manuals forfeit the deposit after 60 days

XBuilt builds retail fit-outs across Toronto, Mississauga, Brampton, Vaughan and the rest of Ontario, with permit and inspection coordination, site supervision and closeout included. If your checklist is half done, request a quote and we will review the lease exhibit and landlord criteria with you.

FAQ

Retail fit-out FAQ

What should be on a retail fit-out checklist?

Settle the split between landlord's and tenant's work, get the landlord's criteria package, confirm deposits, insurance and designated contractors, complete the drawings for landlord review, secure the building and sign permits, release long-lead orders, agree on site rules and plan the closeout documents.

Does a retail fit-out need a building permit in Toronto?

Most interior alterations do. Toronto Building's Express Service covers interior alterations to retail, office and business uses up to 600 square metres with no change in use, with a goal of reviewing eligible applications within 3 business days. Other projects go through the regular streams, which target 15 to 30 business days for complete applications.

How long does landlord approval take for a retail fit-out?

It depends on the lease and the landlord. Published Toronto criteria give the landlord 10 business days for the preliminary submission and 10 for the final drawings, and incomplete packages are not reviewed.

Sources

  1. City of Toronto — Building permit review streams (2026)
  2. Government of Ontario — File a work notice (Notice of Project) (2026)
  3. Bay Adelaide Centre — Retail Tenant Design Criteria (2021, with 2023–2024 updates; posted 2025)
  4. First Canadian Place — Tenant Design & Construction Manual, TDCM100.11 (April 2025)

Start your retail project

Let’s build
your next
store.

Tell us about the unit, the landlord and your opening date. We reply to qualified requests the same business day.

+1 (647) 398-9960 info@xbuilt.ca
Your request goes directly to info@xbuilt.ca.